What work will we be carrying out on campus in March? And how will it affect users of the campus and local residents? Read all about it in Work in Progress.

x

We will continue re-landscaping the outdoor area. Benches will be installed on the square in front of building E. On the side of the canal in front of building G, we will be removing paving slabs and doing excavation work. The low concrete walls in the Green Nose Park will be demolished.  On building A, we are removing the façades on the low-rise building and fitting new façade panels. We will continue work on the steel structure for the central hall between buildings A and B/C/D. We will be refurbishing the three towers of building E internally.

Do you want to find out more? Read all about it in Work in Progress.