The schedule for the erection and dismantling of scaffolding around Building G has been changed. The current schedule is as follows:

Building G

Area (see map below)

Date

Dismantling red area 29/30 August
Erecting green area 30 August - 2 September
Erecting blue area 12 - 16 September
Dismantling yellow area 20 - 27 September
Dismantling green area 19 - 20 October
Dismantling blue area 19 - 21 October

 

Map area

The roof of Building G is being renovated. Scaffolding is needed to ensure that the work can be carried out safely. The erecting and dismantling of scaffolding may cause noise nuisance.

If all goes according to plan, the work should be finished by 21 October. As it will not be possible to work on the roof during stormy weather or heavy rain, the planning may be altered. Changes in the planning will be published on the website.