The sheet piling installation along Nieuwe Achtergracht has come to a halt. A number of obstructions on the bottom of the canal are preventing the contractor from being able to drive the 17 metre long walls into place. A solution is being sought, and as soon as this has been identified, the work will recommence. The walls need to be in place by the end of February, which should allow sufficient time. One small benefit of this is that the access will remain open so long as no work is being carried out. Any updates will be posted on the site immediately.